The Government’s draft National Policy Statement (NPS) for Data Centres was published on 28 October 2026, setting out how decisions on major data centre developments could be made in future. Louise Leyland, director at PWA Planning, summarises the key points.
What is the biggest change for data centre planning?
The most significant change for planners and data centre developers is the proposal for the largest data centres to be considered through the Nationally Significant Infrastructure Project (NSIP) process.
The draft NPS establishes an indicative threshold of 100MW rated IT load capacity, above which data centre schemes are likely to be considered nationally significant and therefore eligible for direction into the NSIP process under section 35 of the Planning Act 2008.
This moves decision-making away from local planning authorities and towards a Development Consent Order (DCO) regime, with decisions taken by the Secretary of State following examination by the Planning Inspectorate.
Why is the National Policy Statement on data centres significant?
This marks an important shift in how the Government views large-scale data centres. Traditionally considered commercial development, they are increasingly being recognised as critical infrastructure that underpins everything from cloud computing to artificial intelligence.
As demand for digital services continues to grow, the Government is signalling that major data centres should be planned and delivered in a similar way to nationally important energy, transport and water infrastructure.
Will this make it easier to get planning consent for data centres?
The proposed changes do not remove the need for thorough environmental assessment. Developers will still need to consider matters such as climate change, biodiversity, flood risk, water use, noise and pressure on the electricity network.
However, the draft NPS introduces a strong presumption in favour of consent for qualifying schemes, provided statutory requirements and mitigation measures are satisfied.
For the planning system, the implications could be significant. Local authorities may see fewer applications for the very largest data centres, while planners involved in infrastructure projects are likely to become increasingly familiar with the DCO process.
Overall, the draft NPS signals the Government’s intention to speed up the delivery of major data centres by recognising them as critical national infrastructure.
The consultation on the draft National Policy Statement for Data Centres runs until 8th January 2027.
If you would like more information on gaining planning consent for data centres in the UK, please get in touch using our contact form or give us a call.